
Pass PRINCE2-Agile-Foundation Exam - Real Test Engine PDF with 52 Questions
Get New PRINCE2-Agile-Foundation Certification Practice Test Questions Exam Dumps
NEW QUESTION 11
Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?
- A. To fail fast, if you are going to fail
- B. To use empiricism, based on knowledge that comes from experience
- C. To build, measure, learn from your experiences
- D. To create a minimum viable product to manage uncertainty
Answer: B
NEW QUESTION 12
How is the 'tailor to suit the project' principle applied in an agile context?
- A. By flexing what is produced to stay in control and deliver value
- B. By emphasizing tolerances on what is being delivered
- C. By using the Agilometer to assess the project environment
- D. By fitting releases into planned management stages
Answer: A
NEW QUESTION 13
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.
- A. 1 and 2
- B. 1 and 4
- C. 2 and 3
- D. 3 and 4
Answer: B
NEW QUESTION 14
Which statement about the 'accept that the customer doesn't need everything' target is correct?
- A. It can result in the early delivery of a minimum viable product
- B. It allows misunderstandings to be dealt with appropriately
- C. It is achieved by managing the culture of the team carefully
- D. It gives confidence on the progress of the project
Answer: B
NEW QUESTION 15
What should be decided when configuring PRINCE2 effectively?
- A. Which areas are not enabled to work with agile
- B. What to remove and where to add guidance
- C. Where to put the emphasis and where to add guidance
- D. What to significantly change to create the right blend
Answer: D
NEW QUESTION 16
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?
- A. Using visualization to display information
- B. Using meeting minutes to share decisions
- C. Using email to document discussions
- D. Using social media to reach more people
Answer: A
NEW QUESTION 17
Which statement explains how the 'learn from experience' principle is applied in an agile context?
- A. It provides guidance on mapping PRINCE2 roles to an agile environment
- B. It focuses on the prioritization and decomposition of requirements
- C. It is supported by the 'inspect and adapt' concept
- D. It integrates releases within management stages
Answer: C
NEW QUESTION 18
Which statement explains the PRINCE2 Agile behavior of 'exploration'?
- A. It seeks out feedback collaboratively from project stakeholders
- B. It displays the progress rate to everyone using burn-down charts
- C. It uses the most effective channel to communicate information
- D. It empowers the project management team at the delivery level
Answer: A
NEW QUESTION 19
Which is a typical characteristic of 'business as usual' work?
- A. It requires a specific dedicated project manager
- B. It is executed by program management
- C. It is delivered by an established team
- D. It is delivered by a temporary team
Answer: C
NEW QUESTION 20
Which statement about the 'protect the level of quality' target is CORRECT?
- A. It is achieved by allowing enough time for testing
- B. It delivers the early realization of benefits
- C. It is achieved by using the same team members
- D. It gives confidence on the progress of the project
Answer: B
Explanation:
Reference:
%20level%20is%20met
NEW QUESTION 21
What term is used to describe boards that display what work needs to be completed for people working on a project?
- A. Information radiator
- B. Work in progress limit
- C. Highlight report
- D. Glad! Sad! Mad!
Answer: C
NEW QUESTION 22
Which BEST describes the senior user role when tailoring the organization theme?
- A. An 'agile sponsor'
- B. A 'coach'
- C. An 'executive sponsor'
- D. A 'super product owner'
Answer: D
NEW QUESTION 23
To help with prioritization, what is MOST important when understanding the difference between scope and quality?
- A. Defining non-functional requirements before functional requirements
- B. Creating non-functional requirements with user stories
- C. Combining functional and non-functional requirements
- D. Differentiating functional from non-functional requirements
Answer: D
NEW QUESTION 24
Which statement about the 'embrace change' target is CORRECT?
- A. It minimizes the time needed to train a new team member
- B. It reduces the planning of dependencies between projects
- C. It reduces testing in order to meet deadlines
- D. It encourages the customer to raise new ideas
Answer: D
NEW QUESTION 25
Which is a key objective of running a workshop?
- A. To encourage collaboration and create the defined outputs from the event
- B. To make day-to-day decisions on behalf of the delivery team within a sprint
- C. To make daily progress visible to the delivery team and key stakeholders
- D. To communicate decisions to the wider stakeholder community
Answer: A
NEW QUESTION 26
Which is often used during a retrospective to capture lessons?
- A. A Kanban board
- B. A burn chart
- C. A Glad! Sad! Mad! board
- D. A Gantt chart
Answer: C
NEW QUESTION 27
Which statement about the 'directing a project' process is CORRECT?
- A. The project board should make decisions based on the Agilometer risks
- B. The project board should increase the stage-level time tolerance
- C. A project board member should fulfill the product owner role within a delivery team
- D. The project board should attend regular project progress meetings
Answer: C
NEW QUESTION 28
What is the definition of a timebox?
- A. A regular event that looks at how processes can be improved
- B. A description of the rate of progress a team is making
- C. A tool to write a requirement in the form of who, what and why
- D. A period where work is carried out to achieve a goal
Answer: D
NEW QUESTION 29
How does the change theme regard change in PRINCE2 Agile?
- A. As a necessity
- B. As disruptive
- C. As something to be avoided
- D. As inevitable
Answer: D
NEW QUESTION 30
Why is Lean Startup included in the 'starting up a project' process in PRINCE2 Agile?
- A. Because it is designed to manage projects, delivering products in timeboxes
- B. Because it enables agile to be used in challenging and uncertain situations
- C. Because running a project and setting up a new business are the same
- D. Because it explains how a small company can grow using traditional technologies
Answer: B
NEW QUESTION 31
......
PRINCE2 PRINCE2-Agile-Foundation Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
PRINCE2-Agile-Foundation Exam Dumps - PDF Questions and Testing Engine: https://www.examcollectionpass.com/PRINCE2/PRINCE2-Agile-Foundation-practice-exam-dumps.html
Real PRINCE2-Agile-Foundation Exam Dumps Questions Valid PRINCE2-Agile-Foundation Dumps PDF: https://drive.google.com/open?id=1Vs-tnmW0S9RkMdypyEq1d4COYU3PVO40