NEW QUESTION 12
How is the 'tailor to suit the project' principle applied in an agile context?
- A. By flexing what is produced to stay in control and deliver value
- B. By using the Agilometer to assess the project environment
- C. By emphasizing tolerances on what is being delivered
- D. By fitting releases into planned management stages
Answer: A
NEW QUESTION 13
Which is an advantage of using the PRINCE2 Agile behavior 'collaboration'?
- A. It ensures that there are no surprises
- B. It allows people to provide cover for one another
- C. It uses experimentation to expand requirements
- D. It uses learning to help improve products
Answer: D
NEW QUESTION 14
Which statement explains the target 'be on time and hit deadlines' for flexible delivery?
- A. It improves the supplier's reputation with the customer
- B. It enables team dynamics to remain the same
- C. It reduces testing in order to meet deadlines
- D. It sets the project baseline at the correct level
Answer: C
NEW QUESTION 15
What is an epic?
- A. The set of products handed over to the users
- B. A detailed user story with high business value
- C. A high-level user story that is quite broad or vague
- D. A prioritized list of requirements to be delivered in a sprint
Answer: C
NEW QUESTION 16
What should the business case state about the minimum viable product (MVP)?
- A. That the MVP must go into operational use
- B. When the MVP will be defined
- C. That the MVP is the same as project viability
- D. What the MVP is
Answer: A
NEW QUESTION 17
How does the change theme regard change in PRINCE2 Agile?
- A. As disruptive
- B. As a necessity
- C. As something to be avoided
- D. As inevitable
Answer: D
NEW QUESTION 18
What term is used to describe boards that display what work needs to be completed for people working on a project?
- A. Information radiator
- B. Highlight report
- C. Glad! Sad! Mad!
- D. Work in progress limit
Answer: B
NEW QUESTION 19
During which process should release planning be done for the FIRST time?
- A. Managing product delivery
- B. Controlling a stage
- C. Initiating a project
- D. Managing a stage boundary
Answer: D
NEW QUESTION 20
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.
- A. 1 and 2
- B. 3 and 4
- C. 2 and 3
- D. 1 and 4
Answer: D
NEW QUESTION 21
Which statement about velocity is CORRECT?
- A. It is shown by the ideal line on a bum-down chart
- B. It is based on the concept of rationalism
- C. It describes how much work is getting done
- D. It tracks the time and cost of a timebox
Answer: C
NEW QUESTION 22
How does agile address the risk associated with the project not being fully understood at the beginning?
- A. By avoiding too much detail at the start
- B. By requiring details at the start
- C. By preventing the analysis of details at the start
- D. By allowing a lot of detail at the start
Answer: C
NEW QUESTION 23
What should be decided when configuring PRINCE2 effectively?
- A. What to significantly change to create the right blend
- B. What to remove and where to add guidance
- C. Where to put the emphasis and where to add guidance
- D. Which areas are not enabled to work with agile
Answer: A
NEW QUESTION 24
Which statement about the 'directing a project' process is CORRECT?
- A. The project board should make decisions based on the Agilometer risks
- B. The project board should attend regular project progress meetings
- C. The project board should increase the stage-level time tolerance
- D. A project board member should fulfill the product owner role within a delivery team
Answer: D
NEW QUESTION 25
Which is a typical characteristic of 'business as usual' work?
- A. It is delivered by an established team
- B. It requires a specific dedicated project manager
- C. It is delivered by a temporary team
- D. It is executed by program management
Answer: A
NEW QUESTION 26
Which statement about the 'keep teams stable' target is CORRECT?
- A. It applies primarily to the long term, such as a project or a program
- B. It is the primary reason why the tolerance for cost is set to zero
- C. It prevents compromising the overall quality level of the product
- D. It results in the early delivery of a minimum viable product
Answer: B
NEW QUESTION 27
Which is a reason for releasing a product into a staging area?
- A. It supports regulatory compliance checking
- B. It enables a phased Waterfall approach
- C. It enables the faster delivery of changes
- D. It supports management by exception
Answer: A
Explanation:
Reference:
%20and%20verification%20process
NEW QUESTION 28
Which BEST describes the senior user role when tailoring the organization theme?
- A. An 'agile sponsor'
- B. An 'executive sponsor'
- C. A 'coach'
- D. A 'super product owner'
Answer: D
NEW QUESTION 29
Which statement about the 'accept that the customer doesn't need everything' target is correct?
- A. It allows misunderstandings to be dealt with appropriately
- B. It is achieved by managing the culture of the team carefully
- C. It can result in the early delivery of a minimum viable product
- D. It gives confidence on the progress of the project
Answer: A
NEW QUESTION 30
What information is NOT typically displayed on a burn chart?
- A. Actual amount of work done
- B. Definition of 'ready'
- C. Effort remaining
- D. Amount of time elapsed
Answer: B
NEW QUESTION 31
Which is often used during a retrospective to capture lessons?
- A. A Glad! Sad! Mad! board
- B. A Gantt chart
- C. A burn chart
- D. A Kanban board
Answer: A
NEW QUESTION 32
......
PRINCE2 PRINCE2-Agile-Foundation Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|