NEW QUESTION 12
How is the 'tailor to suit the project' principle applied in an agile context?

  • A. By flexing what is produced to stay in control and deliver value
  • B. By using the Agilometer to assess the project environment
  • C. By emphasizing tolerances on what is being delivered
  • D. By fitting releases into planned management stages

Answer: A

 

NEW QUESTION 13
Which is an advantage of using the PRINCE2 Agile behavior 'collaboration'?

  • A. It ensures that there are no surprises
  • B. It allows people to provide cover for one another
  • C. It uses experimentation to expand requirements
  • D. It uses learning to help improve products

Answer: D

 

NEW QUESTION 14
Which statement explains the target 'be on time and hit deadlines' for flexible delivery?

  • A. It improves the supplier's reputation with the customer
  • B. It enables team dynamics to remain the same
  • C. It reduces testing in order to meet deadlines
  • D. It sets the project baseline at the correct level

Answer: C

 

NEW QUESTION 15
What is an epic?

  • A. The set of products handed over to the users
  • B. A detailed user story with high business value
  • C. A high-level user story that is quite broad or vague
  • D. A prioritized list of requirements to be delivered in a sprint

Answer: C

 

NEW QUESTION 16
What should the business case state about the minimum viable product (MVP)?

  • A. That the MVP must go into operational use
  • B. When the MVP will be defined
  • C. That the MVP is the same as project viability
  • D. What the MVP is

Answer: A

 

NEW QUESTION 17
How does the change theme regard change in PRINCE2 Agile?

  • A. As disruptive
  • B. As a necessity
  • C. As something to be avoided
  • D. As inevitable

Answer: D

 

NEW QUESTION 18
What term is used to describe boards that display what work needs to be completed for people working on a project?

  • A. Information radiator
  • B. Highlight report
  • C. Glad! Sad! Mad!
  • D. Work in progress limit

Answer: B

 

NEW QUESTION 19
During which process should release planning be done for the FIRST time?

  • A. Managing product delivery
  • B. Controlling a stage
  • C. Initiating a project
  • D. Managing a stage boundary

Answer: D

 

NEW QUESTION 20
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.

  • A. 1 and 2
  • B. 3 and 4
  • C. 2 and 3
  • D. 1 and 4

Answer: D

 

NEW QUESTION 21
Which statement about velocity is CORRECT?

  • A. It is shown by the ideal line on a bum-down chart
  • B. It is based on the concept of rationalism
  • C. It describes how much work is getting done
  • D. It tracks the time and cost of a timebox

Answer: C

 

NEW QUESTION 22
How does agile address the risk associated with the project not being fully understood at the beginning?

  • A. By avoiding too much detail at the start
  • B. By requiring details at the start
  • C. By preventing the analysis of details at the start
  • D. By allowing a lot of detail at the start

Answer: C

 

NEW QUESTION 23
What should be decided when configuring PRINCE2 effectively?

  • A. What to significantly change to create the right blend
  • B. What to remove and where to add guidance
  • C. Where to put the emphasis and where to add guidance
  • D. Which areas are not enabled to work with agile

Answer: A

 

NEW QUESTION 24
Which statement about the 'directing a project' process is CORRECT?

  • A. The project board should make decisions based on the Agilometer risks
  • B. The project board should attend regular project progress meetings
  • C. The project board should increase the stage-level time tolerance
  • D. A project board member should fulfill the product owner role within a delivery team

Answer: D

 

NEW QUESTION 25
Which is a typical characteristic of 'business as usual' work?

  • A. It is delivered by an established team
  • B. It requires a specific dedicated project manager
  • C. It is delivered by a temporary team
  • D. It is executed by program management

Answer: A

 

NEW QUESTION 26
Which statement about the 'keep teams stable' target is CORRECT?

  • A. It applies primarily to the long term, such as a project or a program
  • B. It is the primary reason why the tolerance for cost is set to zero
  • C. It prevents compromising the overall quality level of the product
  • D. It results in the early delivery of a minimum viable product

Answer: B

 

NEW QUESTION 27
Which is a reason for releasing a product into a staging area?

  • A. It supports regulatory compliance checking
  • B. It enables a phased Waterfall approach
  • C. It enables the faster delivery of changes
  • D. It supports management by exception

Answer: A

Explanation:
Reference:
%20and%20verification%20process

 

NEW QUESTION 28
Which BEST describes the senior user role when tailoring the organization theme?

  • A. An 'agile sponsor'
  • B. An 'executive sponsor'
  • C. A 'coach'
  • D. A 'super product owner'

Answer: D

 

NEW QUESTION 29
Which statement about the 'accept that the customer doesn't need everything' target is correct?

  • A. It allows misunderstandings to be dealt with appropriately
  • B. It is achieved by managing the culture of the team carefully
  • C. It can result in the early delivery of a minimum viable product
  • D. It gives confidence on the progress of the project

Answer: A

 

NEW QUESTION 30
What information is NOT typically displayed on a burn chart?

  • A. Actual amount of work done
  • B. Definition of 'ready'
  • C. Effort remaining
  • D. Amount of time elapsed

Answer: B

 

NEW QUESTION 31
Which is often used during a retrospective to capture lessons?

  • A. A Glad! Sad! Mad! board
  • B. A Gantt chart
  • C. A burn chart
  • D. A Kanban board

Answer: A

 

NEW QUESTION 32
......


PRINCE2 PRINCE2-Agile-Foundation Exam Syllabus Topics:

TopicDetails
Topic 1
  • Understand the focus areas in an agile contex
  • Understand key concepts relating to PRINCE2
Topic 2
  • Understand key concepts relating to projects and PRINCE2 Agile
Topic 3
  • Understand how PRINCE2 principles, themes, processes and management products are tailored and/or applied in an agile context
Topic 4
  • Understand the agile ways of working, key terms and techniques

 

Go to PRINCE2-Agile-Foundation Questions - Try PRINCE2-Agile-Foundation dumps pdf : https://www.examcollectionpass.com/PRINCE2/PRINCE2-Agile-Foundation-practice-exam-dumps.html

Dumps Practice Exam Questions Study Guide for the PRINCE2-Agile-Foundation Exam: https://drive.google.com/open?id=1Vs-tnmW0S9RkMdypyEq1d4COYU3PVO40