NEW QUESTION # 57
Which three Cost Collection Flexfield core attributes can be derived during import if not explicitly entered in a transaction document? (Choose three.)
- A. Work Type
- B. Funding Source
- C. Expenditure Type
- D. Capitalizable Flag
- E. Billable Flag
Answer: E
Explanation:
The Cost Collection Flexfield is a descriptive flexfield that captures additional information about project costs. It has three core attributes that are required for every cost transaction: Billable Flag, Expenditure Type, and Capitalizable Flag. These attributes can be derived during import if not explicitly entered in a transaction document, based on various rules and sources such as expenditure type defaults, project type defaults, transaction source defaults, etc. Funding Source and Work Type are not core attributes of the Cost Collection Flexfield, but context-sensitive segments that can be optionally enabled for certain transaction sources or business units. These segments capture additional information about how the costs are funded or what type of work is performed. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-costs.html#OAPFM2356141
NEW QUESTION # 58
Which two privileges are assigned to the Project Plan Management duty in Security Reference Implementation?
- A. Transfer Project
- B. View Project Progress
- C. Allocate Project Expense
- D. Manage Project Plan Resource Assignment
Answer: D
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjm/index.html#_Toc468200732_1_12 Topic - Privileges - This table lists privileges granted to duties of the abstract role Project Management Duty.
Granted Role - Project Plan Management
Privilege - only A and C are listed
NEW QUESTION # 59
Which five steps are required for the File-Based Data Import Integration option?
- A. Import data into various applications.
- B. Download an Excel template.
- C. Install an Excel add-in.
- D. Upload the file to the server.
- E. Populate the spreadsheet with data and generate a CSV file.
- F. Run Process to transfer data to interface tables.
- G. Validate the sheet using the Validate option.
Answer: C
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oefpp/overview.html#External_Data_Integration_Services_for_Oracle_Cloud_Overview
NEW QUESTION # 60
Identify three correct statements about the integration of Primavera P6 Enterprise Project Portfolio Management and Oracle Project Portfolio Management Cloud. (Choose three.)
- A. Billing events flow from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.
- B. Summarized actual quantity and cost flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
- C. Projects and task definitions flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
- D. Project plans and progress flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
- E. Event completion flows from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.
Answer: E
Explanation:
Ref: https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49622/F1125394AN6D254.htm Primavera P6 Enterprise Project Portfolio Management and Oracle Fusion Project Portfolio Management: How They Work Together Use Oracle Fusion Project Integration Gateway to integrate Oracle Fusion Project Portfolio Management with Primavera P6 Enterprise Project Portfolio Management. The integration enables project accountants, project billing specialists, and executives to centrally perform project costing, billing, accounting, and executive reporting tasks in Oracle Fusion Project Portfolio Management while enabling each project manager to perform detailed project planning and scheduling in Primavera P6 Enterprise Project Portfolio Management.
Oracle Fusion Project Integration Gateway ensures data security, integrity, and efficiency by defining a set framework in which data is exported from and imported into Oracle Fusion Project Portfolio Management.
The following table and diagram provide an overview of the flow of information.
Information Type
From Application
To Application
Global integration information
Oracle Fusion Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Management
Projects and task definition
Oracle Fusion Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Management
Summarized project actual quantity and cost
Oracle Fusion Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Management
Project plans and progress
Primavera P6 Enterprise Project Portfolio Management
Oracle Fusion Project Portfolio Management
Billing events
Oracle Fusion Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Management
Event completion
Primavera P6 Enterprise Project Portfolio Management
Oracle Fusion Project Portfolio Management
NEW QUESTION # 61
Your customer wants a team member who is assigned to a project to be able to create and submit a forecast, but not to be able to approve the forecast. What is the default project role that you should assign to the person in the project to meet this requirement? (Choose the best answer.)
- A. Project Administrator
- B. Project Application Administrator
- C. Project Manager
- D. Project Accountant
Answer: C
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapjm/project-administrator-job-role.html#Project_Administrator_privileges Project Manager has duty role 'Project Forecast Approval Duty' assigned but Project Administrator has duty role 'Project Forecast Inquiry Duty' - no approval authority Both roles have duty role 'Project Forecast Management Duty' which enables them to Allow creation, submission, update, and deletion of working versions of project forecasts. (Cloud _Roles_Duties.xlsx)
NEW QUESTION # 62
Your customer has different accounting and project accounting periods, and sometimes enters invoices with an invoice date in the open project accounting and closed accounting periods. Which two statements are true about how project accounting and accounting dates will be populated in such invoices?
- A. Project accounting date is the first day of the first open project accounting period.
- B. Project accounting date is the last day of the open project accounting period.
- C. Accounting date is the same as the original invoice date.
- D. Project accounting date is the same as the original invoice date.
- E. Accounting date is the first day of the first open accounting period.
Answer: B
Explanation:
When an invoice is entered with an invoice date in the open project accounting and closed accounting periods, the accounting date is the same as the original invoice date, but the project accounting date is the first day of the first open project accounting period. This ensures that the invoice is accounted in the correct accounting period and recognized in the correct project accounting period. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-invoices.html#OAPFM2355911
NEW QUESTION # 63
Which four standard objects can you configure to include business specific attributes by using Application Composer for Project Execution Management? (Choose four.)
- A. Project Milestones
- B. Project Gates
- C. Project Deliverables
- D. Project Resource Request
- E. Project Resource Assignment
- F. Project Issues
Answer: A
Explanation:
Application Composer is a tool that allows you to configure standard objects or create custom objects to include business specific attributes for Project Execution Management. Four of the standard objects that you can configure using Application Composer are:
Project Gates: These are checkpoints that mark the completion of a phase or stage in a project lifecycle.
Project Issues: These are problems or risks that affect the progress or outcome of a project.
Project Milestones: These are significant events or achievements that indicate the status or completion of a project or task.
Project Deliverables: These are products or services that are produced or provided as part of a project or task. Project Resource Request and Project Resource Assignment are not standard objects that you can configure using Application Composer. These are features that allow you to request and assign resources for projects and tasks based on various criteria such as availability, qualifications, preferences, etc. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-execution.html#OAPFM2356201
NEW QUESTION # 64
After completing setups in a source environment, your customer wants to move the setup data to a target environment.
Identify the two statements related to task list scope, which you must consider before taking a decision based on the customer requirement.
Response:
- A. A task list can be segmented by a scope value and a task can be performed for each qualifying value of the selected object.
- B. A scope value is used to assign users who can perform a task within an implementation project.
- C. Exported setup data can be filtered by specific scope values if the business object has scope enabled for the setup data export.
- D. Exported setup data cannot be filtered by specific scope values if the business object has scope enabled for the setup data export.
Answer: A,B
NEW QUESTION # 65
You want to export your project plan to Oracle Project Financial Management Cloud after initial scheduling is complete in Microsoft Projects. Identify three conditions that must be met for exporting milestone tasks. (Choose three.)
- A. only one labor resource assignment with 100 effort
- B. lowest-level tasks set up with non-zero duration
- C. percent work complete values of 0 or 100 percent
- D. lowest-level tasks set up with zero duration
- E. only one labor resource assignment with 0 effort
Answer: E
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapex/define-project-management-configuration.html#OAPEX1357147 Topic - Microsoft Project Prevalidation: Explained The following table describes Prevalidation rules for tasks and resource assignments.
Level
Rule
Lowest-level tasks
One labor and multiple expense resources are allowed for a lowest-level task. Remove other resources.
Summary tasks
Only one labor resource with zero allocation is allowed for a summary task. Remove all other resources.
Milestone tasks
No subtasks are allowed under milestone tasks. Milestones must be lowest-level tasks.
Milestone tasks
Milestone tasks must have zero duration.
Milestone tasks
Only one labor resource, with zero effort, is allowed for a milestone task. Remove all other resources.
When exporting milestone tasks, ensure that the tasks:
Are lowest-levels task with zero duration, that is, the same start and finish dates.
Have only one labor resource assignment with zero effort.
Have percent work complete values of 0 or 100 percent. Any other values are set to zero before export.
NEW QUESTION # 66
Select two correct statements about project classifications on a template.
Response:
- A. When a project is created from a template, the required project classifications must be entered.
- B. Project Classification is a mandatory field on a project template.
- C. Set Code is not required for a project class category in a project classification.
- D. Project class category in a project classification must be associated with a Set Code.
Answer: A,C
NEW QUESTION # 67
You have been hired as a project manager for implementing the Project Financial Management and Project Execution Management offering by an organization. The Chief Information Officer of the deploying organization has requested you to explain the benefits of using the implementation project-based approach over the functional area-based approach.
Which two are the main benefits of using the implementation projects within Functional Setup Manager?
- A. Implementation Project helps in assigning responsibility of managing setup data to a broad group of users.
- B. Implementation Project helps you to monitor progress of the setup tasks.
- C. Implementation Project gives you the flexibility to set up different functional areas of the offering at different times.
- D. Implementation Project helps you to use the manage setup data entry in bulk option.
Answer: A
Explanation:
Some of the main benefits of using the implementation projects within Functional Setup Manager are:
Implementation Project helps in assigning responsibility of managing setup data to a broad group of users. You can assign tasks to different users who are responsible for entering and validating setup data for different functional areas of the offering.
Implementation Project helps you to monitor progress of the setup tasks. You can track the status and completion percentage of each task and view the dependencies and prerequisites among tasks. Implementation Project does not give you the flexibility to set up different functional areas of the offering at different times, as this is determined by the configuration package that you select for your implementation. Implementation Project does not help you to use the manage setup data entry in bulk option, as this is a separate feature that allows you to import and export setup data across instances using spreadsheets. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/implement-project-financial-management-applications.html#OAPFM2356051
NEW QUESTION # 68
You are implementing Project Portfolio Management for a global professional services organization. In their Consulting Services line of business, it is common to use resources from different business units based on the skills required. Therefore, cross-charge transactions happen between business units within the same legal entity. Transfer price calculations need to be based on raw costs, with no further adjustments to transfer price.
Identify two setups that can drive this borrowed and lent agreement.
- A. Transfer price basis must be Raw Cost and calculation method must be Rate Schedule.
- B. A document entry such as straight time must be enabled for cross-charge transactions.
- C. Transfer price basis must be Raw Cost and calculation method must be Basis Only.
- D. Transfer price basis must be Burdened Cost, and calculation method must be Burden Rate Schedule.
Answer: C
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-billing-configuration-define-transfer-pricing.html#OAPFM3094619
NEW QUESTION # 69
Your customer has implemented Oracle Project Portfolio Management Cloud recently and they have hired new employees for their Professions Services business. These employees are set up in Oracle Human Capital Management Cloud, but the Project Administrators are unable to add them as resources in the Planning Resource Breakdown Structure.
What are three conditions for new employees to show up in the list? (Choose three.)
- A. All new employees created as persons must have an active supervisor.
- B. All new employees created as persons must have an active project role.
- C. All new employees created as persons must have an active assignment.
- D. All new employees created as persons must be assigned to a department.
- E. Current date is before the effective date of the resource, and you did not enable the "Include people with future-dated effective start dates" option during the search.
Answer: E
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-foundation-configuration-define-project-resource-breakdown-structures.html#OAPFM180158_2 Why can,t I find persons in the list of resources when I enter team members, planning resources, or person rate schedules?
You can,t find persons in the list of resources when you enter team members, planning resources, or person rate schedules in the following situations:
The administrator didn,t assign a department while creating users. Persons must have an active assignment and be assigned to a department in Oracle Fusion Human Capital Management before they can be added as team members or entered as resources on the planning resource breakdown structure or person rate schedule.
The resource isn,t active in Oracle Fusion Human Capital Management because the current date is before the effective date of the resource. If you want to include persons who will start in the future, select the Include people with future-dated effective start dates option when you search for the person.
Persons assigned as project managers aren,t active as of the project start date.
The assignment of the person is terminated, and an appropriate value isn,t set for the number of days to display people with terminated assignments. You can set the profile value appropriately at the site profile level using the Specify Number of Days to Display People with Terminated Assignments task in the Setup and Maintenance work area.
NEW QUESTION # 70
Your customer wants to generate accounting based on project information associated with the transaction for all subledger transactions. Identify three subledger applications for which the project source is available for deriving accounts when configuring subledger accounting. (Choose three.)
- A. Payables
- B. Purchasing
- C. Fixed Asset
- D. Receipt Accounting
Answer: C
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-costing-configuration-define-project-costing-integrations.html#OAPFM3094605 Topic - Deriving Projects-Related Accounts
NEW QUESTION # 71
You are currently involved in the implementation of the Project Financial Management solution for your client organization. Your client organization has two main lines of business: Consulting and Support. Consulting Services and Support Services organizations have different project planning, management, analysis and reporting requirements for the projects that they manage, though the management reporting and transaction processing requirements are the same for both the organizations.
What will be your recommendation?
- A. Define Two Business Units and Two Project Units
- B. Define One Business Unit and Two Project Units
- C. Define One Business Unit and Three Project Units
- D. Define Two Business Units and One Project Unit
Answer: B
Explanation:
The recommendation for this scenario is to define one business unit and two project units. A business unit is an organization that performs one or many business functions such as transaction processing or reporting. A project unit is an organization that manages projects within a business unit or across multiple business units. By defining one business unit and two project units, you can meet the following requirements of the client organization:
The management reporting and transaction processing requirements are the same for both the organizations: This can be achieved by using the same business unit for both the organizations, as the business unit determines the common setups such as ledger, currency, calendar, etc. for transaction processing and reporting.
The project planning, management, analysis and reporting requirements are different for each organization: This can be achieved by using different project units for each organization, as the project unit determines the specific setups such as project types, templates, options, etc. for project planning, management, analysis and reporting. Defining two business units and two project units is not recommended for this scenario, as this would create unnecessary duplication of setups for transaction processing
NEW QUESTION # 72
You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Portfolio Management with tasks and subtasks applicable to each of the phases of the project: Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want to define deliverables for your project requirements that are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works. Identify the two correct statements in this respect.
- A. A deliverable associated with a requirement is not automatically associated with the tasks created for that requirement.
- B. You associate a deliverable with a task, independent of associating a requirement with a task.
- C. A deliverable associated with a requirement is automatically associated with the tasks created for that requirement.
- D. The association of a deliverable with a task is dependent on associating a requirement with a task.
Answer: A
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapem/define-project-deliverables.html#OAPEM1122079 Associate deliverables with one or many tasks or requirements at any level. Associate existing deliverables to tasks or requirements or create deliverables directly for tasks or requirements. You can delete a deliverable in New status if it is not associated with tasks or requirements.
Can deliverables for projects and tasks be inherited from associated requirements?
No. A deliverable associated with a requirement is not automatically associated with the tasks created for that requirement.
You associate a deliverable with a task, independent of associating a requirement with a task.
NEW QUESTION # 73
You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)
- A. 0
- B. 1
- C. 2
- D. 3
Answer: B
Explanation:
Budget 5,000 Actuals 800 Commitment 600
ETC = Budget - Actuals - Commitment
ETC = 5,000-800-600 = 3,600 Budget available for next 4 months = 3,600/4 = 900/month
NEW QUESTION # 74
Identify two correct role templates available on the Oracle Entitlement Server to generate roles for Project Organization Security.
- A. Project Billing Specialist Template for Project Organization Security
- B. Project Accountant Template for Project Organization Security
- C. Project Manager Template for Project Organization Security
- D. Project Administrator Template for Project Organization Security
- E. Project Creator Template for Project Organization Security
Answer: D
Explanation:
Reference https://docs.oracle.com/en/cloud/saas/applications-common/r13-update17d/faser/implementing-security-in-oracle-fusion-project-portfolio-management.html#FASER1722595 Ref to "Securing Project Financial Management and Grants Management Applications" Table lists predefined enterprise roles and the type of security that grants the role access to data in a work area or dashboard.
Enterprise Role
Work Area or Dashboard
Data Security Based On
Project Accountant
Asset
Project business unit
Project Accountant
Costs
Project expenditure business unit
Project Accountant
Revenue
Contract business unit
Project Administrator
Project Financial Management
Project business unit
Project organization
Project Billing Specialist
Invoices
Contract business unit
Project Creator
Project Financial Management
Project business unit
Project organization
Project Management Duty
Project Management Infolet Dashboard
Project assignment
Project Management Duty
Project Performance Dashboard
Project assignment
Project Manager
Project Management Infolet Dashboard
Project assignment
Project Manager
Project Performance Dashboard
Project assignment
Project Manager
Project Management
Project assignment
Project Manager
Project Manager Dashboard
Project assignment
Project Team Member
Project Financial Management
Project assignment
Grants Accountant
Invoices
Contract business unit
Grants Accountant
Revenue
Contract business unit
Grants Administrator
Awards
Contract business unit
Grants Administrator
Contracts
Contract business unit
Grants Administrator
Project Financial Management
Project business unit
Principal Investigator
Awards
Award assignment
Principal Investigator
Contracts
Award assignment
Principal Investigator
Project Financial Management
Project assignment
NEW QUESTION # 75
......